Miss your VMware subscription anniversary and Broadcom adds 20% to the first-year renewal.

Try it freeFull version · $21 once →
What you get: The .xlsx workbook you keep and send to finance: the same 12 formulas live in Excel or LibreOffice, plus a Catch-up plan sheet that shows the cores you pay for but do not have (16-core floor), the…
Updated 2026-10-09 · ReadyStack
Miss your VMware subscription anniversary and Broadcom adds 20% to the first-year renewal. This calculator shows, for your cluster, whether the move to Proxmox VE finishes before that date, and what the renewal costs if it does not.
| Physical cores in the cluster | - |
| Licensed cores (16-core minimum per CPU) | - |
| VMware subscription per year | - |
| Days the migration needs | - |
| Days short of the renewal date | - |
| Renewal you still owe if the migration overruns | - |
| 20% late surcharge if you let it lapse | - |
| VMs per week needed to finish in time | - |
Everything updates as you type. Nothing is uploaded. This runs in your browser.
Full version — $21 once · the .xlsx workbook with a Catch-up plan sheet, one-time payment, not a subscription. See your own answer above first.
16-core minimum per CPU. Broadcom bills the physical cores of every CPU, and never fewer than 16 per CPU (Broadcom KB 313548). Two 12-core CPUs are billed as 32 cores.
20% late-renewal surcharge. If the subscription is not renewed on its anniversary date, Broadcom adds 20% on top of the first year's renewal offer (Techzine, 28 March 2025).
No 72-core minimum. The 72-core order minimum announced for 10 April 2025 was withdrawn the same day; Broadcom kept the 16-core rule (iX / it-daily, 10 April 2025). Many calculators and chatbots still apply 72.
Why a free core calculator is not enough: it multiplies cores by a price, but it never compares your Proxmox VE migration pace with the renewal date. The example price of $135 per core per year is Redress Compliance's list estimate for vSphere Foundation; type the price from your own quote.
The .xlsx workbook you keep and send to finance: the same 12 formulas live in Excel or LibreOffice, plus a Catch-up plan sheet that shows the cores you pay for but do not have (16-core floor), the weeks you really have left after the buffer, and how many VMs will still be on vSphere on renewal day a
One payment, one licence key for this tool. The key is shown right after payment.
Broadcom KB 313548: license the physical cores of every CPU, with a minimum of 16 cores per CPU. Techzine (28 March 2025): a subscription that is not renewed on its anniversary date costs a 20% increase on top of the first year's
Buy the full version — $21I have a keyThis tool is 1 of 267 paid tools in English. All 267 with one key: Freelancer & Small Business Pass — $9.99/month · $79/year · Deadline reminders by email (free)
Need more than this one? ReadyStack Pass opens all 679 files and 561 full versions — $29/month or $199/year. See the Pass →
Paste this code into your page. It runs in your visitor’s browser and stays up to date. Nothing your visitors type is stored.
For businesses: your name and logo instead of ours, and each visitor’s result + e-mail in your inbox (only when they tick consent) — Pro from $19/month. See Pro →
· ReadyStack
Real numbers from this tool, line by line.

An IT manager moving a 4-host vSphere cluster to Proxmox VE at 10 VMs a week is 23 days short of the VMware renewal date, so the company still owes the renewal, 17,280 dollars for a year.
Here is the calculation, from the workbook's own example:
| Result | Value |
|---|---|
| Physical cores in the cluster | 96 |
| Licensed cores (16-core minimum per CPU) | 128 |
| VMware subscription per year | 17,280 dollars |
| Days the migration needs | 98 |
| Days short of the renewal date | 23 |
| Renewal you still owe if the migration overruns | 17,280 dollars |
| 20% late surcharge if you let it lapse | 3,456 dollars |
| VMs per week needed to finish in time | 13.8 |
The inputs were 4 ESXi hosts, 2 CPUs per host, 12 cores per CPU, 135 dollars per core per year, 120 VMs still on vSphere, 10 VMs moved per week, 75 days until the anniversary, and 2 buffer weeks for testing and cutover.
Broadcom licenses VMware Cloud Foundation and vSphere Foundation by physical core, but never fewer than 16 cores per CPU (Broadcom KB 313548). A 12-core CPU is billed as 16. Eight CPUs of 12 cores are 96 real cores and 128 billed cores. The 32 extra cores cost 4,320 dollars a year at the example price. That figure sits on the Catch-up plan sheet.
You may have read that the minimum is 72 cores per order. That change was announced for 10 April 2025 and withdrawn the same day; Broadcom said it was keeping the 16-core rule (iX and it-daily, 10 April 2025). Tools that still apply 72 overstate a small cluster's bill.
A migration plan counts VMs; the bill counts days. If the cutover is not finished on the anniversary, the hosts still need a subscription, so you renew. If you let the date pass and renew later, Broadcom adds 20% on top of the first year's renewal offer (Techzine, 28 March 2025). In the example that is 3,456 dollars on top of 17,280.
The workbook turns your pace into days: (VMs ÷ VMs per week + buffer weeks) × 7. Here that is (120 ÷ 10 + 2) × 7 = 98 days, against 75 days left.
Three situations, same cluster:
If "Days short of the renewal date" is above zero, you have two honest moves. Raise the pace to the figure in "VMs per week needed to finish in time" (13.8 here). Or ask your reseller for a renewal quote before the anniversary instead of letting it lapse, so you do not pay the 20% on top.
The Catch-up plan sheet tells finance how many VMs will still be on vSphere on renewal day at today's pace: 33 in the example, with 8.7 weeks left after the buffer.
The free calculator runs in your browser on your 8 numbers. Nothing is uploaded. The example price of 135 dollars per core per year is Redress Compliance's list estimate for vSphere Foundation, so replace it with your own quote. The workbook holds the same 12 formulas for Excel or LibreOffice.
From 8 inputs and 12 formulas it counts your licensed VMware cores under Broadcom's 16-core-per-CPU rule, prices the yearly subscription, and compares the days your Proxmox migration needs with the days left to the subscription anniversary. It shows the days you are short, the renewal you still owe, the 20% surcharge if you let it lapse, and the weekly pace needed to finish in time.
IT managers and sysadmins who run a small or edge vSphere cluster and are moving it to Proxmox VE, XCP-ng or Harvester. It is built for the weeks before the VMware subscription anniversary, when you must decide whether to speed up the cutover or ask your reseller for a renewal quote before the date passes.
A core calculator multiplies cores by a price and stops. It does not compare your migration pace with the renewal date, it does not tell you that missing the anniversary adds 20% to the first-year renewal, and it does not give the VMs per week you need to finish before that date. This calculator does all three with your own numbers.
The browser page is free and complete for one cluster: licensed cores, yearly bill, migration days, days short, renewal owed, the 20% surcharge and the needed weekly pace. The workbook is a file you keep. It has the same formulas plus a Catch-up plan sheet with the 16-core floor cost, the weeks left after the buffer, and the VMs still on vSphere on renewal day.
In the worked example (4 hosts, 2 CPUs of 12 cores each, $135 per core), the cluster is billed for 128 cores, or $17,280 a year. A lapsed renewal adds 20%, which is $3,456. The workbook is a one-time $21 payment, not a subscription, and you can try the free page with your own numbers before you buy.
One question, answered by the person who built it. Your email only if you want the answer sent.
For a team or company: for an invoice with your company details, a quote or several licences, write to [email protected].
PHP PDF library for EU VAT invoices — Art. 226 checkerCheck one EU invoice against 15 Art. 226 VAT Directive checks in your browser: missing fields, reverse-charge wording in 6 languages, VAT…FreeFull version $60
Freelance Portfolio TemplateEvery commission enquiry - brief, budget band, usage rights and deadline - is stored in your own site database instead of a form host: 8…FreeFull version $129
Proxmox Terraform provider — map dependencies to replacement linesThis browser tool maps VMware vSphere dependencies in Terraform, Packer, and Ansible files to Proxmox VE replacement lines.FreeFull version $29
PCI DSS Log requirements — check Python logs for card dataThis browser tool flags Python logging, print, and raise calls that write sensitive data into logs, with a PCI DSS requirement and fix for…FreeFull version $29
Renpy Release check — check your script freeThis browser tool finds Ren'Py script issues including unescaped brackets and braces, define instead of default, tab indents, and shipped…FreeFull version $29
sepa_pruefkit — offline IBAN, BIC, Gläubiger-ID and USt-IdNr checks for German SEPA exports (Rust, zero dependencies)What you get: This page is the working piece. Full version · $2 →FreeFull version $2ReadyStack
Calculators, templates and deadlines for the rules that change every year — free in your browser.