For EU grant coordinators: 5% of your maximum grant is retained from pre-financing and interim payments stop at 90% — see the euros you carry until the final payment, 60…

Try it freeFull version · $21 →
What you get: enter your start date and up to 4 reporting periods, and every report due date, latest payment date, interim payment and cumulative cash received is laid out by date — saved per grant, ready to hand…
Updated 2026-10-16 · ReadyStack
For EU grant coordinators: 5% of your maximum grant is retained from pre-financing and interim payments stop at 90% — see the euros you carry until the final payment, 60 + 90 days after the project ends.
| Initial pre-financing (gross) | €600,000.00 |
| Retained for the Mutual Insurance Mechanism | €75,000.00 |
| Cash paid on day one (pre-financing minus MIM) | €525,000.00 |
| Interim payment ceiling in euros | €1,350,000.00 |
| Interim payment after reporting period 1 | €750,000.00 |
| Accepted in period 1 but pushed to the final payment by the ceiling | €50,000.00 |
| Cash received before the final payment | €1,275,000.00 |
| Final grant amount (capped at the maximum grant) | €1,480,000.00 |
| Final balance (negative = amount recovered) | €130,000.00 |
| Withheld until the final payment (balance + MIM release) | €205,000.00 |
| Latest days after project end until final payment (60-day report + deadline) | 150 |
| Your cost of carrying that amount until it arrives | €5,054.79 |
Everything updates as you type. Nothing is uploaded. This runs in your browser.
Full version — $21 once: the .xlsx with a dated Payment Calendar: report due dates and latest payment dates for up to 4 reporting periods
Rules used, from the EU Annotated Grant Agreement V2.0 (01.04.2025), Art. 21–22: 5% of the maximum grant retained from the initial pre-financing for the Mutual Insurance Mechanism and released with the final payment · pre-financing + interim payments capped at the Data Sheet ceiling (usually 90%) · periodic report due 60 days after the period · payment within 90 or 60 days of receiving it. Dates are the latest if nothing is suspended (Art. 29).
The .xlsx adds a dated Payment Calendar: enter your start date and up to 4 reporting periods, and every report due date, latest payment date, interim payment and cumulative cash received is laid out by date — saved per grant, ready to hand to your finance office.
One payment, one licence key for this tool. The key is shown right after payment.
EU Annotated Grant Agreement V2.0 (01.04.2025): 5% of the maximum grant retained from the initial pre-financing for the Mutual Insurance Mechanism, interim payments capped at 90% of the maximum grant, periodic report due 60 days a
Buy the full version — $21I have a keyThis tool is 1 of 267 paid tools in English. All 267 with one key: Freelancer & Small Business Pass — $9.99/month · $79/year · Deadline reminders by email (free)
Need more than this one? ReadyStack Pass opens all 679 files and 561 full versions — $29/month or $199/year. See the Pass →
Paste this code into your page. It runs in your visitor’s browser and stays up to date. Nothing your visitors type is stored.
For businesses: your name and logo instead of ours, and each visitor’s result + e-mail in your inbox (only when they tick consent) — Pro from $19/month. See Pro →
· ReadyStack
Real numbers from this tool, line by line.

A Horizon Europe coordinator with a €1,500,000 grant and 40% pre-financing will see €205,000 held back until the final payment, up to 150 days after the project ends. Here is the whole schedule, worked from the rules in the EU Annotated Grant Agreement (AGA V2.0, 01.04.2025):
| Line | Amount |
|---|---|
| Initial pre-financing (40%) | €600,000 |
| Retained for the Mutual Insurance Mechanism (5%) | €75,000 |
| Cash paid on day one | €525,000 |
| Interim payment after period 1 (€800,000 accepted) | €750,000 |
| Accepted but pushed back by the 90% ceiling | €50,000 |
| Withheld until the final payment (balance €130,000 + MIM €75,000) | €205,000 |
| Cost of carrying it at a 6% borrowing rate for 150 days | €5,054.79 |
Two rules do it. First, for Horizon Europe the contribution to the Mutual Insurance Mechanism, 5% of the maximum grant, is deducted from the initial pre-financing and released only at the end of the action. The AGA's own example: on a €1,000,000 grant with 40% pre-financing, €50,000 is retained from €400,000. Second, pre-financing plus interim payments may not exceed the interim payment ceiling in your Data Sheet, usually 90% of the maximum grant. In our case the ceiling is €1,350,000; with €600,000 of pre-financing already counted, the period 1 payment stops at €750,000 even though €800,000 was accepted.
The final periodic report is due 60 days after the last reporting period ends. The granting authority then has the payment deadline in your Data Sheet, 90 or 60 days, to pay. If both run to the last day, the balance plus the MIM release reaches the coordinator 150 days after the project ends (120 days with a 60-day deadline). If the authority suspends the deadline because a report needs fixing (Art. 29), the clock stops and the wait gets longer.
Type your maximum grant, pre-financing rate, the accepted EU contribution per period, the payment deadline and your own borrowing rate. Twelve lines update as you type, in your browser, with nothing uploaded. The MIM rate and the ceiling stay filled in with the Horizon Europe defaults; change them if your Data Sheet says otherwise.
The .xlsx has the same twelve formulas plus a dated Payment Calendar: enter the starting date, the date the agreement entered into force and up to four reporting periods, and you get each period end date, report due date, latest payment date, interim payment and cumulative cash, with a check that the total equals the final grant amount. It is a one-time payment, not a subscription.
If the EU pays after the deadline, the AGA grants late-payment interest at the ECB main refinancing rate plus 3.5 points; amounts of €200 or less are paid only on request within two months. Check your own Data Sheet before you plan: pre-financing rate, ceiling and deadline are set per grant.
It turns your Horizon Europe Data Sheet numbers into a payment schedule. Example: a €1,500,000 grant with 40% pre-financing and €800,000 + €680,000 accepted pays €525,000 on day one and €750,000 after period 1, and withholds €205,000 until the final payment, up to 150 days after the project ends.
Coordinators and grant managers of Horizon Europe projects at universities, research institutes and SMEs who must tell their finance office when EU money arrives and how much the organisation carries until the final payment: 60 days for the final report plus the 90- or 60-day payment deadline in the Data Sheet.
A generic template treats the grant as paid when costs are accepted. Horizon Europe does not: 5% of the maximum grant is retained from the initial pre-financing for the Mutual Insurance Mechanism, and pre-financing plus interim payments stop at the interim ceiling, usually 90%. Everything above that arrives only with the final payment.
The whole schedule for one grant with two reporting periods: day-one cash, the interim payment, the amount the 90% ceiling pushes back, the final balance, the MIM release, the days until the final payment and your cost of carrying it. Nothing is blocked and no sign-up is needed; it runs in your browser.
A one-time $21 .xlsx with a dated Payment Calendar for up to 4 reporting periods: period end dates, report due dates, latest payment dates, each interim payment and cumulative cash received, with a check that the total equals the final grant. It is a one-off payment, not a subscription, and every formula stays visible.
One question, answered by the person who built it. Your email only if you want the answer sent.
For a team or company: for an invoice with your company details, a quote or several licences, write to [email protected].
Section 232 Tariff Calculator 2026 — Steel, Aluminum & Copper Duty on Full ValueSince April 6, 2026 the Section 232 duty is charged on the full customs value, not the metal content (Proclamation 11021). Entering on the…FreeFull version $21TikTok Shop Fee Calculator 2026 — 6% vs 8% Referral Fee Profit CheckFor US TikTok Shop sellers: profit per order and per month after the referral fee, creator commission, returns and the refund admin fee.…FreeFull version $21
Form 8850 due date and WOTC credit for one hireForm 8850 is due 28 calendar days after a start date. During the 2026 WOTC authority lapse the clock still runs.FreeFull version $60
Self Assessment Workbook 2025-26 UK ExcelYour 31 January 2027 Self Assessment bill in one figure — the 2025-26 balancing payment plus your first 2026-27 payment on account — with…FreeFull version $14.99
Construction Project Dashboard Template — Earned Value, Float & RFI Control (Power BI)Your team already pays $14 per user/month for Power BI Pro (Microsoft list price effective 1 April 2025) and it still opens on an empty…FreeFull version $69
Etsy fee Calculator — Etsy Profit Calculator 2026One sale that Etsy attributes to an Offsite Ad costs 15% of the order total (12% once your shop has sold $10,000 in 365 days), up to $100…FreeFull version $21ReadyStack
Calculators, templates and deadlines for the rules that change every year — free in your browser.